Status Reports Fall 2010
General Information
Project name: T/TAC Online
Date: 9/30/10
Prepared by: Dalia Abdulmeguid, Colleen Halverson, Jeffrey Sears, and Christy Stanley
Accomplishments:
Submitted the Performnce Analysis which will be included in the final Performance Analysis/Needs Assessment document.
- Background
- Purpose
- Problem
- Stakeholders
- Review of extant data including Minutes from Sponsor Meeting
- Design team mission, vision and goals
- Next steps
Needs Assessment
- Continued documentation of the Research Plan which details tasks of the focus groups and walk throughs which will provide data for the NA
Confirmed all 3 focus groups for week of October 18th.
- Special Advisory Committee: October 19th. 10 AM- 12 PM
- The Arc of NoVA: October 20th. 12 PM-2 PM
- PEATC: October 21st. 10 AM- 12 PM
Next Steps | Lead | Due Date |
Begin work on 1st Phase of Project Site :
|
Jeff | 10/7 |