| October
17, 2003 |
| Accomplishments |
- Met with Mike Berhmann to
discuss personas and upcoming projects
- Completed and presented Personas
- Updated team norms to include:
project lead and task lead Assigned project leads for the rest of the
semester. -For Use cases it is Justin
|
| Current
Activities |
|
| Progress
on last week goals |
| Complete
use cases - 50% complete |
| Goals
for next week |
|
|