Accomplishments:
  • Completed survey of T/TAC staff software usage
  • Gave button templates to Shuangbao
  • More issues added to the QA database, many issues now have screen shots for better communication of the issue
Plans:
  • Update webshop & www.workshop tutorials as site changes
  • Continue work on content tutorials
  • Run one more usability test
  • Update site QA Issues as more are found or fixed
Issues / Concerns:
  • Lots of fixes to the site needed, many of which will require tutorials to be reconstructed with new screen shots
Other:
 