Accomplishments: |
- Added
43 more issues to the Quality Assurance database. These issue were
uncovered by usability testing and visits with Mary Wilds, Amie Fultcher,
& Shuangbao.
- Further
refined tutorials on creating webshops & courses.
- Compiled
list of T/TAC staff around the state for a survey.
- Developed
survey for T/TAC staff on multimedia software they are familiar with.
- Worked
with Shuangbao to cross-reference our issues list with issues which
have been resolved.
- Developed
outline and instructional strategies for Online Content Development
webshop.
- Completed
Summary of Research Results for Phase One of Online Content Development
evaluation.
|
Plans: |
- Email
survey to TTAC staff. Use results to develop webshops on preparing
multimedia for TTAC Online.
- Schedule
3 more staff for usability tests including their use of the tutorials.
- Update
QA database as issues are resolved.
- Complete
outline of Online Content Development webshop
- Conduct
testing to confirm status of issues which Shuangbao has indicated
have been resolved
- Coordinate
meeting between T/TAC 2 and Mike to prepare for April 20 meeting.Coordinate
|
Issues
/ Concerns: |
- The
Quality Assurance database currently has 100 issues to be addressed.
We may not know the correct priority for these issue for our April
20th event.
- Need to determine
appropriate methods for T/TAC 1 & 2 to work together to complete
site-wide user-perspective testing in preparation for April 20 meeting
and launch.
|
Other: |
|