Accomplishments:
  • Added 43 more issues to the Quality Assurance database. These issue were uncovered by usability testing and visits with Mary Wilds, Amie Fultcher, & Shuangbao.
  • Further refined tutorials on creating webshops & courses.
  • Compiled list of T/TAC staff around the state for a survey.
  • Developed survey for T/TAC staff on multimedia software they are familiar with.
  • Worked with Shuangbao to cross-reference our issues list with issues which have been resolved.
  • Developed outline and instructional strategies for Online Content Development webshop.
  • Completed Summary of Research Results for Phase One of Online Content Development evaluation.


Plans:
  • Email survey to TTAC staff. Use results to develop webshops on preparing multimedia for TTAC Online.
  • Schedule 3 more staff for usability tests including their use of the tutorials.
  • Update QA database as issues are resolved.
  • Complete outline of Online Content Development webshop
  • Conduct testing to confirm status of issues which Shuangbao has indicated have been resolved
  • Coordinate meeting between T/TAC 2 and Mike to prepare for April 20 meeting.Coordinate
Issues / Concerns:
  • The Quality Assurance database currently has 100 issues to be addressed. We may not know the correct priority for these issue for our April 20th event.
  • Need to determine appropriate methods for T/TAC 1 & 2 to work together to complete site-wide user-perspective testing in preparation for April 20 meeting and launch.