T/TAC Group 1 Status as of November 14, 2003
Accomplishments: |
|
Plans: |
|
Issues
/ Concerns: |
In our efforts to simplify the webshop upload process, we eliminated some steps in the webshop creation process. When we presented these ideas to Mike on October 29, he accepted our plans, but added new requirements to our scope. Incorporating these new requirements has placed the finalization of the flowcharts and wireframes by Monday, November 17 at risk. |
Other: |
contact: TTAC-Grp1_Webmaster |